New Connection Procedure

  • 19122 (24x7 Helpline)
  • 011-41999808 Streetlight Emergency No.
  • New Connection Procedure
  • Citizen Survey by NeSDA
  • Home
  • About Us
  • Regulatory & Compliances
  • News & Media
  • Tender
  • Contact Us
  • Apple Store
  • Google Play Store
  • facebook
  • twitter
  • Visit by Appointment

New Connection - BYPL

BYPL_NewConnection_Content
  •  Domestic
  •  Non Domestic
  •  Industrial
  •  Agricultural
 

Getting a Domestic Connection

To apply for a new electricity connection for any residential requirement, all you need to do is follow these simple steps or opt for Online Registration

  Step 1

  •     Domestic Category – Residential / Hostels / Hospitals / Educational Institutions / Religious / Charitable / Others .Applicable as per prevailing DERC tariff order.
  • New Connection request can be raised through different mediums, which are as follows:
    • Call Center (011-39999808)
    • Division Office( Click here to get the divisional office details)
    • Website (www.bsesdelhi.com)
    •  MobileApp ( Click here to download the App)
    • SMS (Type BSESYPNCX send to 5616108)
  • For Load  45KW / 50 kVA and above New connection request only be raised via Online Mode.Click here 
  • List of Documents to be presented for New connection:
    • Any one ID proof mentioned below: AADHAR, Electoral Identity Card ID, Passport, PAN Card, Ration Card with Photograph, Driving License or Photo Identity Card issued by any Govt. agency, If applicant is an Organization: (Certificate of incorporation / registration issued by the Registrar and proof of authorization / resolution of board for authorizing the person.)
    • Any one Proof of Ownership or occupancy of premises mention below: Certified copy of title deed, Certified copy of registered conveyance deed, General Power of Attorney(GPA), Possession  / Allotment letter, Rent receipt not earlier than 3 months along with undertaking that the rent receipt has been signed by the owner or his authorized representative, valid Lease agreement along with undertaking that the lease agreement has been signed by the owner or his representative, Mutation certificate issued by a Government body such as Local Revenue Authorities or Municipal Corporation or land owning agencies like DDA /L&DO,Sub-division agreement. For bonafide consumers residing in JJ clusters or in other areas with no specific municipal address, the licensee may accept either ration card or electoral identity card mandatorily having the same address as a proof of occupancy of the premises
    • Declaration form & application form for new connection is available at division Office also online. Click here  (New connection application form & Declaration form.)
    • Submit the form online along with required documents. In case the applicant is not able to submit application online , Applicant can approach Seva kendra/Connection Desk, available at all our Divisional Offices along with mandatory documents on appointment date and time. At online Seva Kendra the form will be filled online by BYPL executives along with capturing of Applicant’s photo and digital  signature.  Click here for a list of the divisional offices near you.

  Step 2

  • Charges payable for New Connection & Meter Installation in case there is no Commercial & Technical deficiency.
  • The charges payable by the applicant to BSES for New connection depends on the Tariff Category and sanctioned load:

    • Advance Consumption Deposit/ Security Deposit depending on your Sanctioned load and tariff category, as specified in the table (Click here for the table).
    • The normative SLD charges shall be payable by the applicant for taking new electricity connection at LT supply for the connections upto 200KW/215 kVA (Click here for the table).

 

Getting a Non-Domestic Connection

To apply for a new electricity connection for any non-residential requirement, all you need to do is follow these simple steps or opt for Online Registration

  Step 1

  • Non-Domestic Category – Banks /Petrol pumps /Cinemas/ Shops /Chemist /Tailors /Others Applicable as per DERC tariff order.
  • New Connection request can be raised through different mediums, which are as follows:
    • Call Center (011-39999808)
    • Division Office( Click here to get the divisional office details)
    • Website (www.bsesdelhi.com)
    •  MobileApp ( Click here to download the App)
    • SMS (Type BSESYPNCX send to 5616108)
  • For Load  45KW / 50 kVA and above New connection request only be raised via Online Mode Click here

  • List of Documents to be presented for New connection:

    • Any one ID proof mentioned below: AADHAR, Electoral Identity Card ID, Passport, PAN Card, Ration Card with Photograph, Driving License or Photo Identity Card issued by any Govt. agency, If applicant is an Organization: (Certificate of incorporation / registration issued by the Registrar and proof of authorization / resolution of board for authorizing the person.)

    • Any one Proof of Ownership or occupancy of premises mention below: Certified copy of title deed, Certified copy of registered conveyance deed, General Power of Attorney(GPA), Possession  / Allotment letter, Rent receipt not earlier than 3 months along with undertaking that the rent receipt has been signed by the owner or his authorized representative, valid Lease agreement along with undertaking that the lease agreement has been signed by the owner or his representative, Mutation certificate issued by a Government body such as Local Revenue Authorities or Municipal Corporation or land owning agencies like DDA /L&DO,Sub-division agreement. For bonafide consumers residing in JJ clusters or in other areas with no specific municipal address, the licensee may accept either ration card or electoral identity card mandatorily having the same address as a proof of occupancy of the premise

    • Declaration form & application form for new connection is available at division Office also online. Click here  (New connection application form & Declaration form.) 

    • Submit the form online along with required documents. In case the applicant is not able to submit application online , Applicant can approach Seva kendra/Connection Desk, available at all our Divisional Offices along with mandatory documents on appointment date and time. At online Seva Kendra the form will be filled online by BYPL executives along with capturing of Applicant’s photo and digital signature. Click here for a list of the divisional offices near you.

  Step 2

  • Charges payable for New Connection & Meter Installation in case there is no Commercial & Technical deficiency.
  • The charges payable by the applicant to BSES for New connection depends on the Tariff Category and sanctioned load:

    • Advance Consumption Deposit/ Security Deposit depending on your Sanctioned load and tariff category, as specified in the table (Click here for the table).
    • The normative SLD charges shall be payable by the applicant for taking new electricity connection at LT supply for the connections upto 200KW/215 kVA (Click here for the table).
 

Getting an Industrial Connection

To apply for a new electricity connection for any industrial requirement, all you need to do is follow these simple steps or opt for Online Registration

  Step 1

  • New Connection request can be raised through different mediums, which are as follows:
    • Call Center (011-39999808)
    • Division Office( Click here to get the divisional office details)
    • Website (www.bsesdelhi.com)
    • MobileApp ( Click here to download the App)
    • SMS (Type BSESYPNCX send to 5616108)
  • For Load 45KW / 50 kVA and above New connection request only be raised via Online Mode. Click here 

  • List of Documents to be presented for New connection:
    • Any one ID proof mentioned below: AADHAR, Electoral Identity Card ID, Passport, PAN Card, Ration Card with Photograph, Driving License or Photo Identity Card issued by any Govt. agency, If applicant is an Organization: (Certificate of incorporation / registration issued by the Registrar and proof of authorization / resolution of board for authorizing the person.)
    • Any one Proof of Ownership or occupancy of premises mention below: Certified copy of title deed, Certified copy of registered conveyance deed, General Power of Attorney(GPA), Possession  / Allotment letter, Rent receipt not earlier than 3 months along with undertaking that the rent receipt has been signed by the owner or his authorized representative, valid Lease agreement along with undertaking that the lease agreement has been signed by the owner or his representative, Mutation certificate issued by a Government body such as Local Revenue Authorities or Municipal Corporation or land owning agencies like DDA /L&DO,Sub-division agreement. For bonafide consumers residing in JJ clusters or in other areas with no specific municipal address, the licensee may accept either ration card or electoral identity card mandatorily having the same address as a proof of occupancy of the premises
    • Declaration form & application form for new connection is available at division Office also online. Click here  (New connection application form & Declaration form.)
    • Submit the form online along with required documents. In case the applicant is not able to submit application online , Applicant can approach Seva kendra/Connection Desk, available at all our Divisional Offices along with mandatory documents on appointment date and time. At online Seva Kendra the form will be filled online by BYPL executives along with capturing of Applicant’s photo and digital signature. Click here for a list of the divisional offices near you.

  Step 2

  • Charges payable for New Connection & Meter Installation in case there is no Commercial & Technical deficiency.
  • The charges payable by the applicant to BSES for New connection depends on the Tariff Category and sanctioned load:

    • Advance Consumption Deposit/ Security Deposit depending on your Sanctioned load and tariff category, as specified in the table (Click here for the table).
    • The normative SLD charges shall be payable by the applicant for taking new electricity connection at LT supply for the connections upto 200KW/215 kVA (Click here for the table).

 

Getting a Agricultural Connection

To apply for a new electricity connection, all you need to do is follow these simple step or opt for Online Registration

  Step 1

  • New Connection request can be raised through different mediums, which are as follows:
    • Call Center (011-39999808)
    • Division Office( Click here to get the divisional office details)
    • Website (www.bsesdelhi.com)
    •  MobileApp ( Click here to download the App)
    • SMS (Type BSESYPNCX send to 5616108)
  • For Load  45KW / 50 kVA and above New connection request only be raised via Online Mode. Click here

  • List of Documents to be presented for New connection:

    • Any one ID proof mentioned below: AADHAR, Electoral Identity Card ID, Passport, PAN Card, Ration Card with Photograph, Driving License or Photo Identity Card issued by any Govt. agency, If applicant is an Organization: (Certificate of incorporation / registration issued by the Registrar and proof of authorization / resolution of board for authorizing the person.

    • Any one Proof of Ownership or occupancy of premises mention below: Certified copy of title deed, Certified copy of registered conveyance deed, General Power of Attorney(GPA), Possession  / Allotment letter, Rent receipt not earlier than 3 months along with undertaking that the rent receipt has been signed by the owner or his authorized representative, valid Lease agreement along with undertaking that the lease agreement has been signed by the owner or his representative, Mutation certificate issued by a Government body such as Local Revenue Authorities or Municipal Corporation or land owning agencies like DDA /L&DO,Sub-division agreement. For bonafide consumers residing in JJ clusters or in other areas with no specific municipal address, the licensee may accept either ration card or electoral identity card mandatorily having the same address as a proof of occupancy of the premises

    • Declaration form & application form for new connection is available at division Office also online. Click here  (New connection application form & Declaration form.)

    • Submit the form online along with required documents. In case the applicant is not able to submit application online , Applicant can approach Seva kendra/Connection Desk, available at all our Divisional Offices along with mandatory documents on appointment date and time. At online Seva Kendra the form will be filled online by BYPL executives along with capturing of Applicant’s photo and digital signature. Click here for a list of the divisional offices near you.

  Step 2

  • Charges payable for New Connection & Meter Installation in case there is no Commercial & Technical deficiency.
  • The charges payable by the applicant to BSES for New connection depends on the Tariff Category and sanctioned load:

    • Advance Consumption Deposit/ Security Deposit depending on your Sanctioned load and tariff category, as specified in the table (Click here for the table).
    • The normative SLD charges shall be payable by the applicant for taking new electricity connection at LT supply for the connections upto 200KW/215 kVA (Click here for the table).

Confirmation!

You are being redirected to our new request registration page. Please login again and proceed for New Request Registration.

Confirmation!

You are being redirected to the external website, Do you want to continue?

Are you sure that you want to delete this record?

OK
Disconnections Fraud Call - 100056107
  •  
  •  
  •  
 
  • Useful Links
  • Sitemap
  • Privacy Policy
  • Disclaimer
  • KYC Initiative

Copyright © 2023 BSES Delhi. All Rights Reserved   

This website is viewed on IE 11+, Mozilla Firefox, Google Chrome and Safari
                                                    
ICGRC PortalICGRC
Portal
AC Replacement SchemeAC Replacement Scheme
Subsidy OPT-OUTSubsidy
OPT-OUT
CHD - Virtual Call CenterCHD
Virtual Call Center
Your FeedbackYour Feedback
Your FeedbackApply
Online
social media imageSocial Media social media close image
BYPL_Social_Link_Content
  • facebook
  • linkdin
  • twitter
  • youtube