New Delhi, 30 September  2008

Press Release

 

BSES begins work on yet another 66 kV Grid at Bakkarwala in South West Delhi

Capital expenditure of Rs 28 crore earmarked for this state-of-the-art Grid

 

        Foundation stone for BSES’ 66 kV, 60 MVA Bakkarwala Grid in South West Delhi laid

        Grid to be commissioned in a record time of 16 months

        This would be BSES’s 120th Grid – up from 103 in 2002

        Grid to benefit 4 lakh residents of Mundka, Nangloi and Najafgargh, including those residing in DDA’s upcoming Bakkarwala housing complex with 5500 flats and a large number of colonies

        Grid will cater to the needs of existing and proposed commercial and shopping centers, pump houses, sewage treatment plants etc

        SCADA compatible Grid will incorporate the latest advancements in distribution technology

 

The foundation stone for BSES’ next generation 66 kV Bakkarwala Grid station was laid today by the elected representative of the area Shri Mukesh Sharma, MLA, senior government and BSES officials led by its CEO Shri Arun Kanchan.

 

Congratulating BSES for planning a 66 kV Grid in South West Delhi’s Mundka area, Shri Mukesh Sharma  said, “Delhi’s power demand is increasing at a rapid pace because of the across-the-board large scale developmental activity taking place in Delhi This Grid, when completed will not only help improve the power situation – especially in the difficult summer months - of this fast developing area but also cater to its future needs”.

 

“I am pleased to inform that once this state-of-the-art Grid is completed, the power situation in this part of Delhi will  not only substantially improve but will also be commensurate with that of South and East Delhi areas,” he added, while urging people to help BSES “eliminate the menace of power theft.”

 

“The 66 /11 kV Grid station with a capacity of 60 MVA and costing around Rs 28 crore will be constructed in a record time of 16 months - keeping in mind the present and future needs of Mundka and adjoining areas – a fast developing hub of South West Delhi”, said Shri Arun Kanchan, CEO, BSES. He added, “A total of over 11 kms of cable – approximately a distance between Saket and India Gate - will be laid during the construction of this grid. BSES plans on adding another two 66kV Grids in West Delhi - one each at Uttam Nagar and Shiv Vihar in the coming months”.

 

Besides easing the load on the existing Grids in the area, including the one at Nangloi, the proposed grid will further improve the power situation for over 4 lakh residents of Mundka, Najafgargh and Nangloi, including those living in a large number of colonies like Bahrola Vihar. It will also cater the power needs of DDA’s upcoming Bakkarwala Housing Complex - consisting of around 5500 flats in Lok Nayak Puram, existing and proposed Commercial and Shopping centres, Water supply pumping stations Sewage pumping stations and in the area.

 

“The high-tech Grid Station, spread over an area of over one acre, will incorporate some of the latest advancements in distribution technology. This Grid, like all others in BSES’ licensed area will be SCADA compatible and can be remotely operated from the central control room at Balaji Estate, leading to faster resolution of breakdowns and complaints”, said a BSES official.

 

 

According to a BSES spokesperson, “Living upto its commitment to provide world - class distribution infrastructure to its customers – commensurate with Delhi’s global city status and as the host city for the Commonwealth Games 2010, BSES is busy sprucing and augmenting its distribution network. In the past six years, the company has invested over Rs 3500 crore towards this task. Besides deploying cutting edge technologies, the company has also increased the EHV Cables (laid) by 77%, Distribution Transformer Capacity by 37%, LT Lines (laid) by 50%, Shunt Capacitors by 55%, 11 KV Feeders by 38%, Grids by 14%, Distribution Transformers by 24% etc.

 